Progress Timeline

Referendum project updates will be provided here to keep our community informed.

February 2025- Referendum Approved

March 2025- The design team was introduced to the design process, timeline, and project schedules, which were reviewed

April 2025- Architect selection, site review and testing, project scope finalization. Design Meeting Update #1, #2, and #3

May 2025- Fire suppression project being reviewed with the state, summer project list being finalized, and preliminary architectural drawings reviewed. Design Meeting Update #4

June 2025 - The summer project list was finalized, preliminary drawings were reviewed, and the community transparency team continued to meet. Design Meeting Update #5 and #6

July 2025- Summer projects went out to bid, the 50% plan review was held with the team and architects, and the district secured the finances with the lowest possible interest rate. Design Meeting Update #7 and #8

August 2025- Summer projects are wrapping up completion, the 75% plan review was completed, mechanical and electricians were on site to finalize plans. Design Meeting Update #9

September/October 2025- Bid Packages were assembled and are available to contractors in ProCore. A walk-through of the building was available on October 24 for those interested in bidding to view the project areas onsite.

November 2025- During the School Board Meeting on November 17, the final contractors were reviewed and selected for the project.

If you are interested in watching the school board discussion, you can access the video link on Vimeo.

January 2026- The work started at WUHS

January- February 2026 Progress Photos

Communication Updates

Design Meeting Minutes

Completing the work we said.

On time.

Within budget.